UPDATING TO LATEST PRICES 
There may be times during pricing that some of your resource costs may
have changed. As Schedule items use copies of the library resources, these
will not be automatically updated in the same way library items
are. You could update them both in your library and in the Schedule you
are working on, but Fast Estimate offers this timesaving function that
means you only have to make the changes only once.
Selecting the Update to Current Prices function will ensure
that all occurrences of the resource within the currently
selected BOQ will be updated to the value currently set
in the resource library. All dependent values within the BOQ
will be automatically recalculated.
Tips
- To update all resources in the form, click on a column header (or
drag mouse) before selecting the function
|